B
BE.FDU
I need to change the bar in the My Tasks Gantt Chart of Project Web Access
(version 2003). The problem is that "splitted" tasks aren't show as a dotted
line. The tasks is a complete bar thats give a wrong impression of duration.
The My Task view shows the following:
Task A ||||||||||||||||||||||||||||||||||||
Task B ||||
Task C ||||||||||
Thats a problem. In MS Project the Gantt Chart shows this:
Task A ||||||||||||| ..............|||||||||||||
Task B ||||
Task C ||||||||||
How can I realise this in Project Web Access, My Tasks view?
(version 2003). The problem is that "splitted" tasks aren't show as a dotted
line. The tasks is a complete bar thats give a wrong impression of duration.
The My Task view shows the following:
Task A ||||||||||||||||||||||||||||||||||||
Task B ||||
Task C ||||||||||
Thats a problem. In MS Project the Gantt Chart shows this:
Task A ||||||||||||| ..............|||||||||||||
Task B ||||
Task C ||||||||||
How can I realise this in Project Web Access, My Tasks view?