PWA-My Tasks is calculating a wrong duration

M

Macedo

Hello

The Project Manager of the company prefer to handle the tasks per
hour, for example, with tasks of 0.5 hours and 1.2 hours.

The problem is in PWA - My Tasks where resources report 0.5 hours on a
task. The Project distributes the work in the day, for example,
including 0.05 hours at 8:00 am and 0.05 hours at 09:00 am and so on.
This changes the duration of the task of 0.5 hours to 1 day.


Is there a way to change these calculations?
Thanks
 
G

Gary Chefetz

Macedo:

Are you by chance using Fixed duration tasks? What is your service pack
level?
 
M

Macedo

Gary,

I solved the problem.
Some people were filling the% Complete column instead of Actual Work.
Because tasks are small (less than 1 hour) the Project was giving this
effort the whole day, changing the duration of the task.

I removed the %Complete column of the view.

Thanks for the help
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top