Hello
The Project Manager of the company prefer to handle the tasks per
hour, for example, with tasks of 0.5 hours and 1.2 hours.
The problem is in PWA - My Tasks where resources report 0.5 hours on a
task. The Project distributes the work in the day, for example,
including 0.05 hours at 8:00 am and 0.05 hours at 09:00 am and so on.
This changes the duration of the task of 0.5 hours to 1 day.
Is there a way to change these calculations?
Thanks