J
jleifb
I am running I have tested this with various plans and get the same results.
I have tasks in a project plan, I assign a resource to the task. The
resource updates the task Start Date via PWA. This in turns updates the
Finish date. Saves the changes, submits the changes. PM approves the date
change and publishes the project via PWA (Edit Project Properties). Open the
Project Plan via Project Pro 2007, the start date shows the original start
date, but the finish date shows the new finish date. In PWA, the resource
shows the correct dates via My Tasks. But this does not match what is on the
Project Plan.
I am running Project Server 2007 and Project Pro 2007.
Any thoughts?
Thanks,
Josh
I have tasks in a project plan, I assign a resource to the task. The
resource updates the task Start Date via PWA. This in turns updates the
Finish date. Saves the changes, submits the changes. PM approves the date
change and publishes the project via PWA (Edit Project Properties). Open the
Project Plan via Project Pro 2007, the start date shows the original start
date, but the finish date shows the new finish date. In PWA, the resource
shows the correct dates via My Tasks. But this does not match what is on the
Project Plan.
I am running Project Server 2007 and Project Pro 2007.
Any thoughts?
Thanks,
Josh