S
Stefan Pascal
Hello.
I would like to know how can i merge the actual work information
gathered from the self assigned tasks.
Here's an example of my situation:
1. We have a project with some tasks (fixed work) and some resources
assigned to them.
2. At some point another resource(s) decided to work on some tasks they
were not assigned.
3. They use the "My Tasks"->"New Task"->"Select project"->*"Select
existing task"*.
4. The report (into the timesheet) the actual work on this new
"self-assigned task".
5. They submit and import the timesheet as usual.
The problem i can't figure out is this: i can see the "Actual Work"
hours reported by the resource(s) if i use PWA reporting ("Data
Analysis"), but i *can't* see the actual work hours if i open the
project and import all the updates. The task shows with 0 (zero) actual
work hours and with the original assigned resources only.
Is there any way to "merge" the "self-assigned" task with project data?
I mean, it would be perfect if the project would be updated in such a
way it would display the actual work on that task by combining the hours
reported by the original task resource(s) and the hours reported by the
resource(s) that self-assigned this task to them.
Thank you.
I would like to know how can i merge the actual work information
gathered from the self assigned tasks.
Here's an example of my situation:
1. We have a project with some tasks (fixed work) and some resources
assigned to them.
2. At some point another resource(s) decided to work on some tasks they
were not assigned.
3. They use the "My Tasks"->"New Task"->"Select project"->*"Select
existing task"*.
4. The report (into the timesheet) the actual work on this new
"self-assigned task".
5. They submit and import the timesheet as usual.
The problem i can't figure out is this: i can see the "Actual Work"
hours reported by the resource(s) if i use PWA reporting ("Data
Analysis"), but i *can't* see the actual work hours if i open the
project and import all the updates. The task shows with 0 (zero) actual
work hours and with the original assigned resources only.
Is there any way to "merge" the "self-assigned" task with project data?
I mean, it would be perfect if the project would be updated in such a
way it would display the actual work on that task by combining the hours
reported by the original task resource(s) and the hours reported by the
resource(s) that self-assigned this task to them.
Thank you.