B
Beth
[PS 2003]
I've created two task-level custom fields which are progress indicators for
schedule and duration. In the project plan in Project Professional the
fields are working properly and the graphical indicators are displayed. I've
created a PWA view for each of these custom fields. The fields appear in the
views with the appropriate titles, but no data is showing up in the fields.
I've tried Publish All Info, F9/Publish All, and Replublish Assignments
without success. I also have a third field which evaluates Actual Work
against the baseline which is displaying properly in its PWA view. (ie, they
are all task-level Enterprise Text custom fields) Any ideas?
Thanks much-
Beth
I've created two task-level custom fields which are progress indicators for
schedule and duration. In the project plan in Project Professional the
fields are working properly and the graphical indicators are displayed. I've
created a PWA view for each of these custom fields. The fields appear in the
views with the appropriate titles, but no data is showing up in the fields.
I've tried Publish All Info, F9/Publish All, and Replublish Assignments
without success. I also have a third field which evaluates Actual Work
against the baseline which is displaying properly in its PWA view. (ie, they
are all task-level Enterprise Text custom fields) Any ideas?
Thanks much-
Beth