PWA open master project

P

Peggy Cornett

PS 2007 -- In Project Center 2003 I would select multiple projects and open
them as a temporary master project. I know I can open a new project and
insert projects in order to create a master project but I prefer choosing
multiple projects from Project Center. How can I do this in 2007 from
Project Center as I did in 2003?
Thanks,
Peg
 
D

Dale Howard [MVP]

Peggy --

Using the Control key, select the row headers of each project in the Project
Center that you want to include in the temporary master project, and then
click the Edit button. Hope this helps.
 