Anthony
When time is entered on timesheets in the PWA, it overwrites the hours in
Project plan rather than appending it. We imported an existing plan so we
want the hours that were there to stay there and just have the new hours
added. We are using non-managed periods.
Example:
1.Task A has 5 hours in the project plan
2. The plan is imported to project server 2003 sp1
3. 10 hours is entered in the PWA for Task A.
4. The total hours for Task A should be 15 when updates are saved to the
project plan, but it shows 10.
thanks