N
Naomi Nissen
I have a column in the PWA Project view, "% Complete". (This is the
view you get when you double click on the project name to view all the
tasks, not just the summary in the Project Center). I have the same
column in Project Professional - and the % is different by 10%
points! More disturbing, the PWA view has 0% completed on the final 8
tasks, and in PPro, many of those 8 tasks show 100% complete. I've
collaborated 9 times to the sky - collaborate all, republish
assignments, publish assignments - and the difference remains. We do
have issues with the project server spooler turning back
collaboration, but those tasks were 100% complete more than a week
ago, with no spooler messages coming up.
thanks for any insights - Naomi
view you get when you double click on the project name to view all the
tasks, not just the summary in the Project Center). I have the same
column in Project Professional - and the % is different by 10%
points! More disturbing, the PWA view has 0% completed on the final 8
tasks, and in PPro, many of those 8 tasks show 100% complete. I've
collaborated 9 times to the sky - collaborate all, republish
assignments, publish assignments - and the difference remains. We do
have issues with the project server spooler turning back
collaboration, but those tasks were 100% complete more than a week
ago, with no spooler messages coming up.
thanks for any insights - Naomi