Hello,

In PWA under Projects View I can also view external tasks, how do I block
them?

Thanks

Girija
 
D

Dale Howard [MVP]

Girija --

I'm not sure why you want to block external tasks, since they show
dependencies between projects. But if you must, add a Filter to each
Project tasks view in PWA with the structure of the Filter as follows:

External Task Not Equal To Yes

Hope this helps.
 