PWA question re weekdays in Timesheet

A

Adrian

In the timesheet view the week days are only shown if you set the timeframe
to a week - they are not shown when the set timeframe is longer than a a
week - can this be adjusted to always show week days?

Thanks

Adrian
 
D

Dale Howard [MVP]

Adrian --

Project Server will display the day of the week, along with the date, if you
set the time period to only one week. If you set the time period longer
than one week, the system displays the date only. I know of no way around
this. Sorry.
 