Hi,
I am using Project Server 2007's resource center to display resource
availability data, and I am finding considerable differences between
what I see in PWA and what I see in MS Project. For instance:
A particular resource shows up in PWA as having 8 hours work assigned
for each of two projects on a certain date. These two projects are
part of a Master Project. If I open each project individually in MS
Project, one of them is inconsistent with the Resoure Center. In MS
Project I see zero hours assigned on a certain date, and I see 8 hours
on the same date in Resource Center.
The OLAP cube has been processed after making the last change to these
projects.
Also, when I check resource usage in the master project, the totals
don't add up correctly in the "Other Projects and Assignments"
summary. The aggregated value is always much higher than the sum of
the lines. Why? There are no filters applied to my view.
Why am I seeing these differences? I assume there is a different
source for data shown in PWA's Resource Center and for the data shown
in MS Project, but I can't figure out why these large discrepancies
are showing up...
Thanks in advance,
Fernando
I am using Project Server 2007's resource center to display resource
availability data, and I am finding considerable differences between
what I see in PWA and what I see in MS Project. For instance:
A particular resource shows up in PWA as having 8 hours work assigned
for each of two projects on a certain date. These two projects are
part of a Master Project. If I open each project individually in MS
Project, one of them is inconsistent with the Resoure Center. In MS
Project I see zero hours assigned on a certain date, and I see 8 hours
on the same date in Resource Center.
The OLAP cube has been processed after making the last change to these
projects.
Also, when I check resource usage in the master project, the totals
don't add up correctly in the "Other Projects and Assignments"
summary. The aggregated value is always much higher than the sum of
the lines. Why? There are no filters applied to my view.
Why am I seeing these differences? I assume there is a different
source for data shown in PWA's Resource Center and for the data shown
in MS Project, but I can't figure out why these large discrepancies
are showing up...
Thanks in advance,
Fernando