pwa Task window in Outlook

J

Jane

Project Server 2007 - Office 2007

We are setting up Project Server but will not being using the Timesheet
component. I have modified the Project Web Access Permissions to not display
links to Timesheet functionality and also disabled Timesheet functionality
itself.

Is there anyway to turn-off/disable/hide the Timesheet tab on the Project
Web Access Task window that is opened in Outlook when double-clicking a task?
If it is there people will click and try to use...


Tks
Jane
 