S
Studer
Hello,
I’m working with PWA 2003 and I have a doubt about updating the tasks of my
project. The question is that for example I have a task that was planned to
last one week, with 4h work each day (20h total). When updating the task, my
resource says he worked much more that planned, lets say 4 days 8h each day
(32h total) and he will still need 15h to complete his work (on the
“Remaining Work†field of the task).
I’ve noticed that MsP automatically divides the total “Remaining Work†by a
large amount of days (20 or more) increasing the duration of my task
immensely.
Any idea what’s the criterion PWA uses to automatically increase the
duration of my task?
Should my resources transmit for example with a note to the project manager
the information that he needs to plan more work to be done instead of filling
the "Remaining Work" field?
Thank you very much.
Studer
I’m working with PWA 2003 and I have a doubt about updating the tasks of my
project. The question is that for example I have a task that was planned to
last one week, with 4h work each day (20h total). When updating the task, my
resource says he worked much more that planned, lets say 4 days 8h each day
(32h total) and he will still need 15h to complete his work (on the
“Remaining Work†field of the task).
I’ve noticed that MsP automatically divides the total “Remaining Work†by a
large amount of days (20 or more) increasing the duration of my task
immensely.
Any idea what’s the criterion PWA uses to automatically increase the
duration of my task?
Should my resources transmit for example with a note to the project manager
the information that he needs to plan more work to be done instead of filling
the "Remaining Work" field?
Thank you very much.
Studer