A
Anthony
We imported an existing project into project server. If a user is assigned to
a task that starts on 1/1 with no actual time, then they enter in time on say
2/1, project is adding a delay of a month and pushing their end date out. How
can we stop this from happening. We are migrating people to project server
for project and time tracking ,but when they enter time for the first time,
delays are added and screwing up the plan.
a task that starts on 1/1 with no actual time, then they enter in time on say
2/1, project is adding a delay of a month and pushing their end date out. How
can we stop this from happening. We are migrating people to project server
for project and time tracking ,but when they enter time for the first time,
delays are added and screwing up the plan.