PWA Time Period settings

R

Reuter

Using MSProject2003ent.

*I’ve tried to reword this entry from previous post, hope I explained it
better this time.

My company is using a fiscal calendar which they(SAP) chose to start on the
“second Sunday in October†. In project/PWA I can only set the (Time Period)
to start on “Sunday†not the first or Second Sunday. Most Fiscal calendars
start on the first Sunday in October but for some reason my company uses the
first week of October to do SAP maintenance. How and where do I make changes
in PWA so project calendar first time period starts 10/12/08 and ends
10/25/09?
 