PWA Time Sheet

S

Sally

PWA will not accept actual hours for a specific project. Admin>Customize PWA
allows the default method for reporting progress to be changed at the PM's
discretion. Tools>Customize>Published Fields on the project is set to Actual
Work Done and Work Remaining. I first published the project plan and they
went back to change the tracking method. That didn't work so I created a new
one and set the tracking method before publishing it. Still no dice. Help
please.
Thanks.
 
D

Dale Howard [MVP]

Sally --

Have you tried Collaborate - Publish - Republish Assignments with this
project? Let us know.
 
S

Sally

Dale,

I tried republish assignments and it didn't work BUT my expectations were
probably off. I expected to see a time sheet with individual days for the
actual work and remaining work tracking method. When I selected hours of
work per time period, I saw what I expected. Duh! Thanks so much.
 
D

Dale Howard [MVP]

Sally --

Thanks for your perserverance! :)




Sally said:
Dale,

I tried republish assignments and it didn't work BUT my expectations were
probably off. I expected to see a time sheet with individual days for the
actual work and remaining work tracking method. When I selected hours of
work per time period, I saw what I expected. Duh! Thanks so much.
 