PWA will not accept actual hours for a specific project. Admin>Customize PWA
allows the default method for reporting progress to be changed at the PM's
discretion. Tools>Customize>Published Fields on the project is set to Actual
Work Done and Work Remaining. I first published the project plan and they
went back to change the tracking method. That didn't work so I created a new
one and set the tracking method before publishing it. Still no dice. Help
please.
Thanks.
allows the default method for reporting progress to be changed at the PM's
discretion. Tools>Customize>Published Fields on the project is set to Actual
Work Done and Work Remaining. I first published the project plan and they
went back to change the tracking method. That didn't work so I created a new
one and set the tracking method before publishing it. Still no dice. Help
please.
Thanks.