PWA - Timesheet - Actuals not balancing.

N

nde

Hi all,

In PWA - 2003 version SP2a - while in view resources assignment view, we
Actuals on the left pane do not balance with the total of the right pane for
certain tasks. The issue is for one specific resource, others do not seem to
have the issue.

Number of the right pane comes from the previous weeks and we are able to
balance manually with MSProject.

How is the number on the left pane calculated ?



Example:

Left pane:
Project ABC - Task 123
Work = 70
Actual Work = 30
Remaining Work = 40

Right Pane (Entire project timeline selected):
Project ABC - Task 123
Actual Work = 25.5 (Last column on the right pane)

this 25.5 balance with the number in MSPRoject.

Thanks,
nde
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top