B
Blake 20
Time Period Setting: Managed Time Periods
Problem: The PWA Timesheet view is showing a check mark indicator for
completion for task while there still are remaining hours for the resource in
the .mpp file (PRO).
What Happen? The resource ran out or hours and the task did roll off the
Current Task view in PWA. However, I realized that I needed to add more hours
so I increased the 0 remaining work hours to XX for the resource because this
is an operational project that is on going throughout the year.
Thereafter I republished the assignments (did not work) and then I tried
publishing all information. No avail.
My goal is to get task(s) showing back into the PWA Resource Timesheet,
Current Task view and have the check mark indicator removed.
Thank you!
Problem: The PWA Timesheet view is showing a check mark indicator for
completion for task while there still are remaining hours for the resource in
the .mpp file (PRO).
What Happen? The resource ran out or hours and the task did roll off the
Current Task view in PWA. However, I realized that I needed to add more hours
so I increased the 0 remaining work hours to XX for the resource because this
is an operational project that is on going throughout the year.
Thereafter I republished the assignments (did not work) and then I tried
publishing all information. No avail.
My goal is to get task(s) showing back into the PWA Resource Timesheet,
Current Task view and have the check mark indicator removed.
Thank you!