M
Matt Kennedy
We are just starting to look into the capability in PWA that will allow our
project team members to update % work complete on thier assigned tasks. I
found that under Admin > Manage Views I can tailor the "Timesheet View". I
have added the Duration and % Complete columns to the view but they neither
column will display any data in them. Being able to show the current task
duration is the more important of the two to show. I have done a Collaborate
(as the team member). Any thoughts on why certain columns remain blank?
project team members to update % work complete on thier assigned tasks. I
found that under Admin > Manage Views I can tailor the "Timesheet View". I
have added the Duration and % Complete columns to the view but they neither
column will display any data in them. Being able to show the current task
duration is the more important of the two to show. I have done a Collaborate
sure that was not the problem. I also logged out and logged back in to PWAPublish > All Information from the project plan a number of times to be
(as the team member). Any thoughts on why certain columns remain blank?