P
P
Never seen this problem before:
PWA Timesheet is confirmed by project resurce to be correct. No changes
submitted is pending for approval. Time periods are closed and actuals are
protected so project manager shouldnt be able to change it.
Allthough it shouldnt be possible, the actuals protected and actual work in
file shows appx 100 hrs more than PWA in a timeperiod closed before the
resource even got a user.
Any clue what happend?
Doing some testing i figured out that for this particular project file it is
possible to manipulate actual work by:
1. adding a new task
2. adding actual work to the new task
3. assigning a new resource to the plan.
Why? And how can i stop it? Are there more possible ways to manipulate
actual work and actual work protected that I am not aware of?
PWA Timesheet is confirmed by project resurce to be correct. No changes
submitted is pending for approval. Time periods are closed and actuals are
protected so project manager shouldnt be able to change it.
Allthough it shouldnt be possible, the actuals protected and actual work in
file shows appx 100 hrs more than PWA in a timeperiod closed before the
resource even got a user.
Any clue what happend?
Doing some testing i figured out that for this particular project file it is
possible to manipulate actual work by:
1. adding a new task
2. adding actual work to the new task
3. assigning a new resource to the plan.
Why? And how can i stop it? Are there more possible ways to manipulate
actual work and actual work protected that I am not aware of?