MS Project seems to add actual work at the rate of planned work for blank
cells of PWA Timesheet entries. The added actial work only shows up in
Project.
It does not add these hours to the Team Members PWA Tasksheet.
Normal project files seem to fill in the blank gaps with 0's.
Is this by design ?
How can stop project from adding actual hours to Admin tasks when the
timesheet has blank cells ?
 