B
bane
Hi,
I am working with PS2007 SP1. I have several groups that update a
schedule on a weekly basis. They currently use the My Tasks view to
update the Start, Finish and %. Each task has a single resource
assigned and each task also has a single predecessor. When a group
updates their start date, and I approve and publish the task, it keeps
the original start date and duration but pushes out the end date by
the difference between the original start and the new start. When a
group member then shows progress on the task, the Actual Start is
populated with the original start and not the Start date that the
member submitted. It seems to be splitting the task (dotted line on
the gantt) so the Start date remains the same, then there is the
split, and then the task is shown.
My question is: Is there anyway to have the Actual Start be updated
by a resource or will it always remain the same and show a split?
I need to track the duration of the actual start and actual finish,
but the actaul start isn't being populated with updates by the
resource.
Thanks in advance.
JC
I am working with PS2007 SP1. I have several groups that update a
schedule on a weekly basis. They currently use the My Tasks view to
update the Start, Finish and %. Each task has a single resource
assigned and each task also has a single predecessor. When a group
updates their start date, and I approve and publish the task, it keeps
the original start date and duration but pushes out the end date by
the difference between the original start and the new start. When a
group member then shows progress on the task, the Actual Start is
populated with the original start and not the Start date that the
member submitted. It seems to be splitting the task (dotted line on
the gantt) so the Start date remains the same, then there is the
split, and then the task is shown.
My question is: Is there anyway to have the Actual Start be updated
by a resource or will it always remain the same and show a split?
I need to track the duration of the actual start and actual finish,
but the actaul start isn't being populated with updates by the
resource.
Thanks in advance.
JC