A
Al
Why does the tool allow you enter time against a close task in All Task
display mode? Really hoping the solution is not a best practice approach...
We are in managed time period so user cannot enter time when the period is
closed but they can be in a open reporting period, display all tasks and
enter time against closed tasks.
What is the best approach to prevent users from entering time against closed
tasks? This maybe a best practive type of answer but here is the senario..
Resource are now hip to the fact of displaying All Task in the Task View as
opposed to displaying Current Task (which is set to only allow 10 business
days in advance). When PWA users are in the All Task View, the system allows
them to enter in time against closed tasks which comes down to project
managers mining their task updates and rejecting the tasks on closed tasks.
Current Task View does not show completed task:
Set Current tasks to display. (Configured to 10 days ahead)
All Task display shows completed task and allow you to enter time against
them:
Set All tasks to display.
Notice the timesheet cells are open and allows edits to the completed time....
Any ideas on an approach? I was thinking to force all users to use the
Incomplete Task filter which will show only task they need to work on in the
current and all task view... The downfall is that once a task is complete.
They cannot see the total hours entered for a task unless the choose the All
task display and All task filter...
Why does the tool allow you enter time against a close task?
Please let me know if further clarification is needed.
display mode? Really hoping the solution is not a best practice approach...
We are in managed time period so user cannot enter time when the period is
closed but they can be in a open reporting period, display all tasks and
enter time against closed tasks.
What is the best approach to prevent users from entering time against closed
tasks? This maybe a best practive type of answer but here is the senario..
Resource are now hip to the fact of displaying All Task in the Task View as
opposed to displaying Current Task (which is set to only allow 10 business
days in advance). When PWA users are in the All Task View, the system allows
them to enter in time against closed tasks which comes down to project
managers mining their task updates and rejecting the tasks on closed tasks.
Current Task View does not show completed task:
Set Current tasks to display. (Configured to 10 days ahead)
All Task display shows completed task and allow you to enter time against
them:
Set All tasks to display.
Notice the timesheet cells are open and allows edits to the completed time....
Any ideas on an approach? I was thinking to force all users to use the
Incomplete Task filter which will show only task they need to work on in the
current and all task view... The downfall is that once a task is complete.
They cannot see the total hours entered for a task unless the choose the All
task display and All task filter...
Why does the tool allow you enter time against a close task?
Please let me know if further clarification is needed.