PWA version of Resource Assignment view?

A

anovak

I have been using a resource assignment view within a master project
that essentially provides a comprehensive list of assignments by
resource across all projects by start date.

Is that possible from either the project center or resource center in
the PWA to provide this type of display? This would be for a mgt
person who wants to see what everyone is working on either in their
group or all groups within the enterprise, not just an individuals
tasks in either the timesheet view.

Thanks,
Andy Novak
University of North Texas
 
D

Dale Howard [MVP]

Andy --

Navigate to the Resource Center page in PWA and then click View resource
assignments in the sidepane on the left. Select the resources whose
assignments you wish to see and click the Apply button. Hope this helps.
 
A

anovak

My question though about this is whether or not you can view by start
date (not by project) so that a person can see what tasks they have
coming up in date order, regardless of project. You can do that in
the Resource Assignment view.

Thanks,
Andy
 
D

Dale Howard [MVP]

Andy --

When you apply the Summary view on the View resource assignments page in
PWA, the default grouping is by Resource Name and then by Project Name. To
mimic what you see in the Resource Usage view, click the View Options tab on
the View resource assignments page and set the Then by grouping to None.
Does this help? Let us know.
 
A

anovak

Dale,
Thanks a bunch! It appears to work properly for the resources. You
know another post I made was a question about being able to see all
projects opened at the same time within project center:

p1
t1
t2
t3
p2
t1
t2
t3

I understand that this isn't possible right now in PWA, correct?

Thanks,
Andy
 