PWA view - Percentage complete

W

Webdev2000

Thanks for reading my question.....

In the pwa website when the user marks a task as 100% complete, I understand
that it does not update the main task table, instead it updates a temp table
and the project manager gets a request for approval. Once the project manager
approves, it updates the main table as 100% complete against the task.

I am looking for the right PSI call to simulate the user marking the task as
100% complete in PWA website. Thanks again lot for your help.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top