PWA Views showing date AND time for no apparent reason and more...

A

anovak

In at least one of the views I'm using (Project Assignment Summary),
Start and Finish dates are displaying both date AND time. In this
instance there is no option to toggle between show date and not show
date. Strange. How do I turn that off?

I also noticed that some views provide a means to specify a default
filter and some don't. And the ones that do sometimes have many fields
available and some only the Enterprise Outline Codes. Could someone
please clear this all up for me as well?

Also... how do you remove the ghant (spelling?) part of the view --
just show the data to the left.

Thanks,
Andy Novak
University of North Texas
 
G

Gary L. Chefetz [MVP]

Andy:

The answer to your first two questions is that the views in PWA are
inconsistently implemented. Please don't ask for logic as there is none.<g>
The best explanation I can give you is sloppy programming and quality
control. You can't remove the Gantt chart, however you can mostly hide it
using the splitter bar offset setting in the Modify View page. Set this to
the maximum 1000 and it will appear to the far right of the grid.
 
A

anovak

Thanks Gary. Can I modify those "canned" views so that I CAN change
the date format, etc.?

Thanks,
Andy
 
G

Gary L. Chefetz [MVP]

Andy:

All the modification you can do, you can do through Admin > Manage Views. If
you don't see the option there, it's not available.
 