PWA views

M

May

Is there a way to view task information (successors & predecessors in
particular) to members of PWA in a similar format to the project task etnry
view.
 
A

Andrew Lavinsky

If you're talking about a split screen, like the Project Professional Task
Entry view, then no. You can however expose the predecessor and successor
fields in PWA views.

Would that work?

-A
 
M

Marc Soester [MVP]

Hi May,

in addition to Andrew's post, you can also view the predecessors /
successors of a task within the "My Task" view when you drill down into the
Task details
hope this helps
 
M

May

Hello both:

Yes, I was thinking of a split screen as it is more convenient to the end
users to view the successors and predecessors of the tasks assigned to them.
Yet drilling down from my task should work.

Thanks
 