P
Paul Shamus
I have Project Server 2007 setup and integrated with MOSS 2007. We are
already starting to use PWA and have run into some permission issues that I
can't seem to figure out. From what I understand, when a project is created
on PWA the user's permission level on the associated workspace depends on the
role that user has within that project itself. If a user is a member of the
team but does not specifically have a task assigned to them, they will have
the Readers permission level assigned to them on the workspace. It is only
when a task is assigned that the permission level changes to Contributor.
However, for the majority of our projects, everybody in the company (around
100 people) should be allowed to contribute. How can I make this work
without having to disable automatic synchronization of permissions between
PWA the the workspace?
already starting to use PWA and have run into some permission issues that I
can't seem to figure out. From what I understand, when a project is created
on PWA the user's permission level on the associated workspace depends on the
role that user has within that project itself. If a user is a member of the
team but does not specifically have a task assigned to them, they will have
the Readers permission level assigned to them on the workspace. It is only
when a task is assigned that the permission level changes to Contributor.
However, for the majority of our projects, everybody in the company (around
100 people) should be allowed to contribute. How can I make this work
without having to disable automatic synchronization of permissions between
PWA the the workspace?