T
Thomas
Hi,
I am facing the problem implementing a PWA view on a project schedule
(project view, not timesheet etc!) that shall display only the tasks
in the next 4 weeks. (another view shall display next 3 months)
Therefore I created a new project view in PWA named "next 4 weeks".
Fields: task name, start, finish, resource name...
Filter should be like...
start ... greater or equal to TODAY
finish ... less or equal to IN4WEEKS (calculated task-field in MSP;
not a published field)
This works in MSP, but not in PWA, as I can only enter fixed dates in
PWA project view-filters!?
Even this does not work in my PWA, as it even does not show an empty
table. Looks more like an error.
Any faults in my thoughts?
Purpose is a vacation schedule for my department. (50 people)
MSP access and schedule managed by secretary. All other colleagues
should access via PWA.
As this schedule is quite big for 50 people I want to apply 2 views
for this project in pwa:
next 4 weeks, next 3 months
Any people that need more details can view the complete schedule or
apply individual filters.
Best solution would be a calender view in PWA....
Help
Thomas
We're using Project / Server 2003
I am facing the problem implementing a PWA view on a project schedule
(project view, not timesheet etc!) that shall display only the tasks
in the next 4 weeks. (another view shall display next 3 months)
Therefore I created a new project view in PWA named "next 4 weeks".
Fields: task name, start, finish, resource name...
Filter should be like...
start ... greater or equal to TODAY
finish ... less or equal to IN4WEEKS (calculated task-field in MSP;
not a published field)
This works in MSP, but not in PWA, as I can only enter fixed dates in
PWA project view-filters!?
Even this does not work in my PWA, as it even does not show an empty
table. Looks more like an error.
Any faults in my thoughts?
Purpose is a vacation schedule for my department. (50 people)
MSP access and schedule managed by secretary. All other colleagues
should access via PWA.
As this schedule is quite big for 50 people I want to apply 2 views
for this project in pwa:
next 4 weeks, next 3 months
Any people that need more details can view the complete schedule or
apply individual filters.
Best solution would be a calender view in PWA....
Help
Thomas
We're using Project / Server 2003