Q: help on Gantt charts (linking tasks)

M

MarkD

Hey,

I'm using Visio 2000 Gantt Chart Shapes. when joining two
tasks, I use the "link lines" object. the problem is, it
always connects the tasks by starting the line on the RHS
of the previous task and connects it to the LHS on the
next task. Connecting to the next task what I want the
line to do is come from above, not from the left, ie:

(Bad ascii artwork to follow)

it does this:

| |----------------
|--->| Task 2
|----------------

I want it to do this:

|
|
v
|----------------
| Task 2
|----------------

can I change this in visio?

thanks,
-Mark
 