I
ITG_Mike
We are running Project Server 2003. We currently have self-assignment (Assign Myself to an Existing Task) turned off (because the feature has numerous bugs). We are testing for when we might enable this feature in the future
Let's say a resource assigns themselves to an existing task and then enters time in their task list. They update that row for the PM to approve and update into the project. The PM notes a problem with the hours entered (not with the assignment itself) and rejects the update from the resource
The hours and the task self-assignment are both then rejected. The resource can make the requested changes to the task hours, but is unable to update the row again (They get a message that the task cannot be updated because the PM has declined the new task request)
The Resource is also unable to add the task assignment again, since the (now rejected) assignment is still on their task list
How does the resource escape this situation? They need to charge time to a task, but cannot update the one assignment they have to that task
Mike
Let's say a resource assigns themselves to an existing task and then enters time in their task list. They update that row for the PM to approve and update into the project. The PM notes a problem with the hours entered (not with the assignment itself) and rejects the update from the resource
The hours and the task self-assignment are both then rejected. The resource can make the requested changes to the task hours, but is unable to update the row again (They get a message that the task cannot be updated because the PM has declined the new task request)
The Resource is also unable to add the task assignment again, since the (now rejected) assignment is still on their task list
How does the resource escape this situation? They need to charge time to a task, but cannot update the one assignment they have to that task
Mike