M
me
I have resources who don't work 100% of their time on a project but I'm
having trouble understanding how to put this information into Project 2000
A typical scenario is the person is available 40% of their time, spread over
the whole week. So overall its 2 days availability , but they can actually
spread this time over the whole week as they choose
What I have done is set the max units to the resource to 40%.
The problem is when I look at the resource usage report the resource usage
doesn't seem to be right. So for example on a 1 day duration task, they are
only working 3.2 hours when it should read 7 hours.
On the Gantt chart it is marked Person's name [40%]
What I've tried to resolve this..
I then go into Task Information and change resources for that person to be
100% , not 40% , the resource graph now seems correct (it shows 100% work on
that day with 40% only available) but the resource usage sheet still only
shows 3.2 hours when it should be a full working day
Whats the correct way to enter the data in that sort of scenario?
Any advice on the above would be appreciated.
Also, Is there any way of allowing the tasks to be flexible to take account
of the fact the the person can spread the work over an entire week? ie as
long as the work in the overall week doesn't add up to more than 40% of their
time its ok
The tasks are currently all marked as Fixed Units, Effort driven by the way,
in case this is a factor in all this. thanks
having trouble understanding how to put this information into Project 2000
A typical scenario is the person is available 40% of their time, spread over
the whole week. So overall its 2 days availability , but they can actually
spread this time over the whole week as they choose
What I have done is set the max units to the resource to 40%.
The problem is when I look at the resource usage report the resource usage
doesn't seem to be right. So for example on a 1 day duration task, they are
only working 3.2 hours when it should read 7 hours.
On the Gantt chart it is marked Person's name [40%]
What I've tried to resolve this..
I then go into Task Information and change resources for that person to be
100% , not 40% , the resource graph now seems correct (it shows 100% work on
that day with 40% only available) but the resource usage sheet still only
shows 3.2 hours when it should be a full working day
Whats the correct way to enter the data in that sort of scenario?
Any advice on the above would be appreciated.
Also, Is there any way of allowing the tasks to be flexible to take account
of the fact the the person can spread the work over an entire week? ie as
long as the work in the overall week doesn't add up to more than 40% of their
time its ok
The tasks are currently all marked as Fixed Units, Effort driven by the way,
in case this is a factor in all this. thanks