J
Joy
If a project (say A) has a sub project (say B) inserted into it. A task in B
(B-3) is one of the predecessors of a task in A (A-2). Also, a task in A
(A-1) is also one of the predecessors of A-2. When I view task drivers of
A-2, I can see both A-1 and B-3 in the list. In the list, there is a link for
A-1 and no link for B-3. I can be easily directed to A-1 by simply clicking
the link, but how can I move to B-3?
Is what MS Project supposed to be designed? Or is there some setting I have
to change to view the link for an externally linked task?
Thanks
(B-3) is one of the predecessors of a task in A (A-2). Also, a task in A
(A-1) is also one of the predecessors of A-2. When I view task drivers of
A-2, I can see both A-1 and B-3 in the list. In the list, there is a link for
A-1 and no link for B-3. I can be easily directed to A-1 by simply clicking
the link, but how can I move to B-3?
Is what MS Project supposed to be designed? Or is there some setting I have
to change to view the link for an externally linked task?
Thanks