Is there anyone who knows how to get the day by day work for the
planned work and for the baselines (1 - 10)? In the MSP_ASSIGNMENTS
table I just have the interval time and the total value of work in the
interval. I do not have the detail for each day just like in the
MSP_WEB_WORK table. Is there an equivalent in the "Project Client
Tables" ?
Thanks