G
Greg
If you use the WW date format(e.g. w5/1), have you noticed
that MS Project doesn't correctly handle W53 which occurs
this year? It shows all dates in w53 '03 as being in
w1 '04, which throws off all dates in 2004 by one week
(later). The Gantt bars show the correct date, but the
Start/Finish columns do not.
I'm trying to develop a workaround for this problem that
still uses the WW date format. Any help would be greatly
appreciated.
Thanks,
Greg
that MS Project doesn't correctly handle W53 which occurs
this year? It shows all dates in w53 '03 as being in
w1 '04, which throws off all dates in 2004 by one week
(later). The Gantt bars show the correct date, but the
Start/Finish columns do not.
I'm trying to develop a workaround for this problem that
still uses the WW date format. Any help would be greatly
appreciated.
Thanks,
Greg