Question: How to calculate % Complete and % Work Complete?

J

Jan De Messemaeker

Hi,

My first reaction is: Don't. Never do. Project does that, it's not your job.
This being said, this is how Project does it
%Complete = 100 * Actual Duration / Duration
%Work Complete= 100 * Actual Work / Work

Hope this helps,
--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 
M

Merry

Thanks Jan.

The following question is how to calculate the Actual Duration?

Thanks,
Merry
 
M

Merry

Hi Jan,

I mean the whole project's Actual Duration. Is there any formula to do this?

Thanks,
Merry
 
J

Jan De Messemaeker

Hi,

Customize one of the custom duration fields with the formula =[Actual
Duration] and make sure the formula is applied to summary tasks and the
project summary task. The latter will show the project total.
Hope this helps,

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 
J

JulieS

Pardon me for bumping in. If you display the project summary task
( Tools > Options, View tab) and then show the tracking table,
you'll see total actual duration is already calculated for you at
the project summary task line as well as for all other summary
tasks.

Julie
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top