Can anyone help with this simple problem?
Why does the Duration box in the Task Form have a question mark after
the estimated duration?
Typically I enter new tasks in the Task Form. My default Task Type set
to Fixed Work. I assign a Resource and enter the Work in the fields
provided. If the resource is not fully available, I adjust the Units.
The Duration box then gives me an estimate of how long the task will
take to complete. Nice. For example a 1 day task assigned to a 20%
resourse will take 5d to complete. But Project displays "5d?" I don't
understand why sometimes there is a ? after the duration estimate and
sometimes not. Any ideas?
Tks,
Cole
Why does the Duration box in the Task Form have a question mark after
the estimated duration?
Typically I enter new tasks in the Task Form. My default Task Type set
to Fixed Work. I assign a Resource and enter the Work in the fields
provided. If the resource is not fully available, I adjust the Units.
The Duration box then gives me an estimate of how long the task will
take to complete. Nice. For example a 1 day task assigned to a 20%
resourse will take 5d to complete. But Project displays "5d?" I don't
understand why sometimes there is a ? after the duration estimate and
sometimes not. Any ideas?
Tks,
Cole