A
a
Hi
We are trying to use MS project to determine the manloading in a PM
department where PMs work on different projects.
I have the following questions:
- The projects are assigned as "Duration Fixed" tasks with a specific number
of hours to be spent. However, when you include vacation time to a certain
ressource, a message box is telling me that duration will change. Is there a
way to force MS Project to re-calculate the % units for this ressource based
on this constraint-without changing duration?
- Is there a way to show the Work Load Bars, on the Ressoruces Graph sheet,
colored differently for each task assigned to a specific ressource over a
peiord of time (other than the blue allocated and the red overallocated ones
?) - Meaning, I would like to see the bars colored with fours different
colors , one for each project the ressoruce is assigned to work on ?
Thanks a lot for your very much appreciated help.
Fayez
We are trying to use MS project to determine the manloading in a PM
department where PMs work on different projects.
I have the following questions:
- The projects are assigned as "Duration Fixed" tasks with a specific number
of hours to be spent. However, when you include vacation time to a certain
ressource, a message box is telling me that duration will change. Is there a
way to force MS Project to re-calculate the % units for this ressource based
on this constraint-without changing duration?
- Is there a way to show the Work Load Bars, on the Ressoruces Graph sheet,
colored differently for each task assigned to a specific ressource over a
peiord of time (other than the blue allocated and the red overallocated ones
?) - Meaning, I would like to see the bars colored with fours different
colors , one for each project the ressoruce is assigned to work on ?
Thanks a lot for your very much appreciated help.
Fayez