T
Tom
Sorry about all the questions, but the task of getting this done was
assigned to me yesterday... due today.
Here is the scenario. I have tasks with resources assigned of certain
duration. If I have two tasks starting on 1/1 with a duration of 10 days and
I assign one a resource with 50% and the other 100%, I would want the end
date of the first to be 1/20 and the second 1/10 when leveled.
Is this doable?
assigned to me yesterday... due today.
Here is the scenario. I have tasks with resources assigned of certain
duration. If I have two tasks starting on 1/1 with a duration of 10 days and
I assign one a resource with 50% and the other 100%, I would want the end
date of the first to be 1/20 and the second 1/10 when leveled.
Is this doable?