J
Jerry Arnone, PMP
Although I have allot of PM experience I have not had to do allot of the
scheduling and maintaining the actual project plans so I have a couple of
questions regarding baselines.
I understand the concept of baselines and what they are for. Lets say I am
going to make some major schedule changes after I have the set the first
baseline. I know to copy the Baseline into Baseline1 by using “Save interim
planâ€. I then make the changes to my schedule (lets say I added 4 tasks and
changed the dates on a couple of tasks) for example. So I then save the
baseline again after I made changes by selecting “save baseline†& “selected
tasks†Should I save those changes to the Baseline or Baseline1 plan?
--
scheduling and maintaining the actual project plans so I have a couple of
questions regarding baselines.
I understand the concept of baselines and what they are for. Lets say I am
going to make some major schedule changes after I have the set the first
baseline. I know to copy the Baseline into Baseline1 by using “Save interim
planâ€. I then make the changes to my schedule (lets say I added 4 tasks and
changed the dates on a couple of tasks) for example. So I then save the
baseline again after I made changes by selecting “save baseline†& “selected
tasks†Should I save those changes to the Baseline or Baseline1 plan?
--