S
Skip W
We are running MSP 2003 Project & Server SP2. We are tracking hours per day
and forcing PMs to use it, but we are not using managed time periods. Since
we are not using managed time periods, if I execute Sync to Protected Actuals
will the actuals in the plan be restored to those in PWA for the entire
duration of the project, or will the command do nothing?
Thanks
and forcing PMs to use it, but we are not using managed time periods. Since
we are not using managed time periods, if I execute Sync to Protected Actuals
will the actuals in the plan be restored to those in PWA for the entire
duration of the project, or will the command do nothing?
Thanks