M
Merry
Hi,
I have encountered an issue.
In EPM (PWA), Resource A updated his task1 to 100% complete, and I saw him
Save & Submit task1.
Then I am the project owner, I went to EPM (PWA), I approved task1 under
Task Updates.
Then I went to Project Center, in the project plan enquiry screen, task1 is
still 0% complete.
What is the reason? EPM admin suggested us to publish the plan every time
after we approved task update. Is this correct?
Thanks,
Merry
I have encountered an issue.
In EPM (PWA), Resource A updated his task1 to 100% complete, and I saw him
Save & Submit task1.
Then I am the project owner, I went to EPM (PWA), I approved task1 under
Task Updates.
Then I went to Project Center, in the project plan enquiry screen, task1 is
still 0% complete.
What is the reason? EPM admin suggested us to publish the plan every time
after we approved task update. Is this correct?
Thanks,
Merry