S
Shane
Hi All,
We are using Project Server 2007 (Feb CU).
One of our projects wants to use more than one calendar where, for example,
we have resources in one country working a y 9 hour day and resources in
another country working an 8 hour day. When I try to create a second base
calendar I am unable to set the working day duration to the correct figure
without altering the other.
I am sure I am doing this wrong so if someone can point me in the right
direction on how best to do this, I would appreciate it.
Cheers
Shane
We are using Project Server 2007 (Feb CU).
One of our projects wants to use more than one calendar where, for example,
we have resources in one country working a y 9 hour day and resources in
another country working an 8 hour day. When I try to create a second base
calendar I am unable to set the working day duration to the correct figure
without altering the other.
I am sure I am doing this wrong so if someone can point me in the right
direction on how best to do this, I would appreciate it.
Cheers
Shane