Question Regarding Multiple Bill Rates for Work Resources

T

Tim Mccoy

I have work resources in my shared resource pool that bill differently
depending on what role they are performing and what client they are billing
to.

Any idea how to properly represent this is my resource pool?

Thank you!
 
J

Jim Aksel

On the resource sheet, double click on a resource name.
Pull the cost tab.
You will see additional Tabs A-E. Each of these tabs can be used to
establish different rate schedules for the resource. Each rate tab can
contain its own set of dates for rate changes.

To use the rates, I do it from the Task Usage View. Insert the Cost Rate
Table column. You can now assign resources to different rate tables
depending on the task assignmnet. You can also do this from the Resource
Usage View. You can mix and match different resources to different cost rate
tables as desired on each task.


--
If this post was helpful, please consider rating it.

Jim Aksel, MVP

Check out my blog for more information:
http://www.msprojectblog.com
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top