M
Merry
Hello,
An inactive resource always brings me a message when i open MS project 2007.
I checked and definitely I found that inactive resource was assigned some
tasks. But I suppose the resource had updated the task progress to 100%
before he left. Is there any way I can know the resource really updated the
task progress to 100%?
Thanks
Zhang
An inactive resource always brings me a message when i open MS project 2007.
I checked and definitely I found that inactive resource was assigned some
tasks. But I suppose the resource had updated the task progress to 100%
before he left. Is there any way I can know the resource really updated the
task progress to 100%?
Thanks
Zhang