Hello,
I have an excel file and I am loading the data into MS Project. In the excel
file I have Resource information, Start and End dates and number of hrs
required for each task. Everytime I do the import MS Project changes either
the duration(Start and End Dates) or then number of hrs required based on the
"Schedule" settings under Task -->Options.
Is there any way to prevent this from happening?
Thank you in advance for your time,
Nick