W
waqas sarwar
Hi Gurus.
Thanks for your already replies to our post. I come up with another
question for you.
Question # 1. I am wondering about the Schedule Backup in the server setting
of the MPS 2007, The schedule backup only update the version of the archieved
projects when some change is made into it. for example i made some changes in
proejct on 17th then on schedule backup i backed up and then no changes till
24 but my schedule back up is running daily, But when i go to the
Administrator Backup see the lastest version is dated 17th not the 24th. So i
think my question is clear that Schedule Backup only backup the project when
some changes made in it as compare to the previous backup verions.
thanks
waqas
Thanks for your already replies to our post. I come up with another
question for you.
Question # 1. I am wondering about the Schedule Backup in the server setting
of the MPS 2007, The schedule backup only update the version of the archieved
projects when some change is made into it. for example i made some changes in
proejct on 17th then on schedule backup i backed up and then no changes till
24 but my schedule back up is running daily, But when i go to the
Administrator Backup see the lastest version is dated 17th not the 24th. So i
think my question is clear that Schedule Backup only backup the project when
some changes made in it as compare to the previous backup verions.
thanks
waqas