J
J Burford Fields
Hi,
Is there a place where I can get more information on baselining
features of Project Professional 2003 and Project Server 2003?
I've read the administrators guide and three good books on Project
Server, but have not been able to clarify well enough how the various
baseline features work.
What I want to do is to only baseline each phase of a project once it
has been scoped and a work authorization has been issued. We baseline
the initiation phase because we can estimate how long the initiation
phase is going to take. We may not have an accurate idea of what we
want in the final products to be, and what work will be required
beyond the initiation phase, until we complete requirements analysis,
the WBS process, then come back and shake out the priorities. Once we
have a project plan, we want to baseline the next phase.
My preference would be to leave the baseline for the initiation phase
as-is. I want to baseline just the tasks related to the next phase.
The obvious thing, it seems to me, is to select the tasks, use the
"baseline sellected tasks" feature and save them as a new baseline.
Someone else suggests that I should add them to the previous baseline,
but when I approach doing this there is a warning message saying I'm
about to "over-write" the previous baseline.
Backing away from this, I wanted to find some documentation as to how
more than one baseline will work with EVMS (presuming each baseline
encompasses different tasks), but am coming up empty.
Anybody been through this who can shed some light on it?
Is there a place where I can get more information on baselining
features of Project Professional 2003 and Project Server 2003?
I've read the administrators guide and three good books on Project
Server, but have not been able to clarify well enough how the various
baseline features work.
What I want to do is to only baseline each phase of a project once it
has been scoped and a work authorization has been issued. We baseline
the initiation phase because we can estimate how long the initiation
phase is going to take. We may not have an accurate idea of what we
want in the final products to be, and what work will be required
beyond the initiation phase, until we complete requirements analysis,
the WBS process, then come back and shake out the priorities. Once we
have a project plan, we want to baseline the next phase.
My preference would be to leave the baseline for the initiation phase
as-is. I want to baseline just the tasks related to the next phase.
The obvious thing, it seems to me, is to select the tasks, use the
"baseline sellected tasks" feature and save them as a new baseline.
Someone else suggests that I should add them to the previous baseline,
but when I approach doing this there is a warning message saying I'm
about to "over-write" the previous baseline.
Backing away from this, I wanted to find some documentation as to how
more than one baseline will work with EVMS (presuming each baseline
encompasses different tasks), but am coming up empty.
Anybody been through this who can shed some light on it?