K
krishnas
Hi,
I've following two questions on the duration calculated for a task:
1. When I assign resources to 80%, the duration is being shown in
decimal values like 23.47 days. How can I make project display it as an
integer rounded off to the nearest value?
2. When I reverted resource for task from 80% to 100%, the old computed
value for the parent task is still in decimal. For example, I have two
tasks that have 2 days of duration. The parent task is still displaying
fractional values. Pressing F9 didn't change it and I cant change the
value manually myself as it is not editable.
3. My management requires the effort to be in 100% as well as 80% to
recommend corrective actions. Is there a mechanism I can display two
columns for the duration for easier review of the plan.
Appreciate if someone can give me pointers on addressing this.
TIA,
krishna
I've following two questions on the duration calculated for a task:
1. When I assign resources to 80%, the duration is being shown in
decimal values like 23.47 days. How can I make project display it as an
integer rounded off to the nearest value?
2. When I reverted resource for task from 80% to 100%, the old computed
value for the parent task is still in decimal. For example, I have two
tasks that have 2 days of duration. The parent task is still displaying
fractional values. Pressing F9 didn't change it and I cant change the
value manually myself as it is not editable.
3. My management requires the effort to be in 100% as well as 80% to
recommend corrective actions. Is there a mechanism I can display two
columns for the duration for easier review of the plan.
Appreciate if someone can give me pointers on addressing this.
TIA,
krishna