A
amara sharif
I have spent hours hunting down a solution please help!!!
I want RAG indicators to highlight if a task is behind schedule / on schedule etc...
The issue that I am having : I want to compare the finish date to the CURRENT DATE? is this possible? surely there must be a default field that stores the current live date?
i.e. i want to say: If the task finish date is less than the current date & is less than 100% complete, flag as RED?
I want RAG indicators to highlight if a task is behind schedule / on schedule etc...
The issue that I am having : I want to compare the finish date to the CURRENT DATE? is this possible? surely there must be a default field that stores the current live date?
i.e. i want to say: If the task finish date is less than the current date & is less than 100% complete, flag as RED?